Current Plan: The current Plan Dates after a Re-plan or moved by the Master Schedule Drum and Accepted in the MS Drum.
Current Schedule: These are the current dynamic dates of the currently running Started project.
Expected Finish Date: The maximum date for any task in the schedule. This might not necessarily be the project’s Final Task.