Project Dashboard Dates: What do the Dates Mean?

Original Planned Dates or Actual Start Dates before a Re-Plan.

Planned Dates: The current Dates after a Re-plan or moved by the Dynamic Drum and Accepted in the Drum.

Schedule Dates: These are the current dates of the Current Status.

The Expected Finish Date is the maximum date on the calendar of any Task in the schedule. Not necessarily the Final task.

 

 

 